Client: McDonald Holdings
Architect: Sheridan Woods Architects
Structural Engineer: Eamonn Doyle & Associates Consulting Engineers
Value: €1.6 million

Start: 1 March 2005
Completion: Ongoing

Description: Project consists of the demolition of the previous filling station, construction of a new filling station in place of the old, including offices on top of the new filling station. Kelly & O'Callaghan Limited prepared the pre-tender cost estimates, Bills of Quantities and on-going Project Management.